WHAT IS THIS PROJECT?
The Wichita Transit Network Redesign is a project that will result in a detailed plan to guide Wichita Transit over the next decade.
Wichita Transit periodically conducts a comprehensive systemwide analysis to identify existing challenges and opportunities for improvement. This project will identify local and regional transportation needs, challenges, and opportunities, create a cohesive planning effort, and prioritize short to long-term transit investments.
HOW LONG IS THIS PROJECT?
The Wichita Transit Network Plan is a year-long project.
The Wichita Transit Network Redesign (TNR) began in 2013 and is scheduled to launch in August 2026, following an 18-month planning process that concluded in winter 2025. Between October 2023 and February 2025, Wichita Transit conducted a comprehensive evaluation of its operations and service area demographics. Public input gathered throughout the process helped shape the final recommendations.
DISCOVERY PHASE

FALL 2023
KICKOFF PROJECT
Define project vision, goals, and purpose.
COMMUNITY ENGAGEMENT
Understand community needs.

WINTER 2023
ANALYZE EXISTING AND EVOLVING CONDITIONS
Review transit system, usage, demographics, and travel patterns.
CONCEPTS PHASE

SPRING 2024
DEVELOP SHORT-RANGE ROUTE CONCEPTS
Identify potential service improvements.
COMMUNITY ENGAGEMENT
Share concepts and obtain feedback.

SUMMER
DEVELOP FUTURE GROWTH SCENARIOS
COMMUNITY ENGAGEMENT
Share draft recommendations.
DEVELOMENT PHASE

FALL 2024
DEVELOP DRAFT RECOMMENDATIONS
Select concepts based on community input and cost/benefit.

FINALIZE RECOMMENDATIONS
Develop final report with recommendations.

WINTER 2025
ENGAGEMENT
Connecting Wichita public engagement activities.
Stakeholder & Public Meeting
Share draft Service recommendations.
IMPLEMENTATION

SPRING 2026
RECOMMENDED SERVICE CHANGES
Capital improvements, sevice scheduling & run times,
route names, The HUB (new transit center).

SUMMER 2026
FULL LAUNCH
August 2026.
GET INVOLVED
The project includes robust community engagement.
You can get involved by taking a survey, attending pop-ups and public meetings, and listening in on stakeholder discussions. Information gathered from these activities will be used to develop the recommendations to improve your transit experience.
Route Renaming Survey
When the new Transit Center is serving as the Hub for our transit network, all routes will change slightly. We would like to use this unique opportunity to simplify route names and your responses will help guide our next steps for renaming the bus routes.
(From now through April 2026)
COMPLETED OUTREACH EVENTS
On-board rider survey: January 23-25, 2024
Online survey #1: January 23-February 26, 2024
Online survey #2: May 1-31, 2024
Oaklawn Family Day: May 4, 2024
Open Streets Nomar: May 5, 2024
Pop-up information sessions at Downtown Transit Center: May 7-8, 2024
Pop-up information sessions at Wichita State University: May 7, 2024
Open house public meeting: May 7, 2024
Council presentation: January 16, 2025

RESOURCES
View project reports and handouts.
As the project progresses, documents detailing findings and recommendations will be posted here.